- Location: Twickenham
- Project type: Kitchen Refurbishment
- Project Duration: 3.5 weeks
We were tasked with full kitchen refurbishment project in Twickenham TW1. Here are some photos of the project on different stages.
Kitchen TW1 BEFORE
Kitchen Twickenham BEFORE
1. Preparation works:
Existing old kitchen. There are a lot of cracked floor tiles, boiler pipework is visible and not enough electrical power sockets above the work surface.
Electrical works tw1
Plastering works tw1
Laying floor underlay tw1
Tiles removed tw1
2. Removal and electrical works:
- remove floor tiles
- remove old kitchen cabinets
- remove some kitchen appliances
- strip of wallpaper
- rewire all sockets and switches
- start skimming walls
Fitting floor underlay
Kitchen cabinets installation
Fitting wooden floor
Fitting wooden floor TW1
3. Flooring and plumbing works:
- adjusting pipework for sink
- washing machine installation
- radiator installation
- wooden floor fitting
- new upvc window installation
- skirting fitting
- bespoke MDF cabinet to cover boiler and pipe works behind
Wooden floor fitting
Tiling around sink
Fitting kitchen cabinets
Extractor hood installation
Bespoke boiler cabinet
Appliances installation
4. Cabinets fitting and painting:
- fitting floor cabinets
- installation of all appliances
- painting walls and skirting
- tiling splashback and window sill
- grouting and silicon
- connect sink and taps
- cleaning and removing floor protections
5/5
We can only mirror the great reviews about Max and his team. Max, with his catch phrase ‘Everything’s possible’ and Naz, finished our kitchen which presented a number of problems They worked through the issues to an exceptional standard ensuring we were happy with each step and we are truly delighted with the finish. Thanks Guys – we’ll be back!
Diane B.Happy customer from Twickenham